Roland Elek
November 9, 2026
10 minutes

How Much Does It Cost to Build Out a Commercial Kitchen

Stainless steel kitchen exhaust duct and hood inside a commercial kitchen ready for build out

A commercial kitchen build out costs $200 to $350 per square foot in hard construction cost for quick-service. Full-service kitchens cost $250 to $400, per Timeless Construction's 2026 pricing. Kitchen equipment adds $75,000 to $500,000 or more. Hood, plumbing, and electrical systems drive the total. Florida plan review and permits then set the schedule.

Key Takeaways

  • Hard construction runs $200 to $450 or more per square foot, depending on the restaurant concept.
  • Kitchen equipment is a separate budget of $75,000 to $500,000 or more.
  • A Type I hood costs $5,000 to $20,000 to install, and fire suppression adds $2,000 to $5,000.
  • Soft costs add 12 to 20 percent on top of hard construction cost.
  • Permitting takes 30 to 60 days, and equipment lead times run 8 to 16 weeks.

How Much Does a Commercial Kitchen Build Out Cost?

Hard construction cost runs $200 to $450 or more per square foot, depending on the concept. Timeless Construction, a North Carolina contractor, publishes those 2026 figures for three restaurant types. Builders Group Construction reports a national restaurant build out range of $180 to $475 or more per square foot. Any commercial kitchen build out cost estimate starts with the concept, because kitchen complexity moves the rate.

Quick-service kitchens sit at the low end because one hood and a short cooking line limit the mechanical work. Full-service concepts with several cooking stations and a bar move a restaurant build out into the upper ranges. Specialty concepts with charcoal grills or wood-fired ovens cost the most. The table below shows the three ranges.

Commercial Kitchen Hard Construction Cost by Restaurant Concept
ConceptHard Cost per Sq FtKitchen Features
Quick-service or fast-casual$200 to $350One hood and limited cooking lines
Full-service casual dining$250 to $400Multiple cooking stations, expanded hood and suppression, bar plumbing
Specialty or multi-concept$300 to $450+Charcoal grills, wood-fired ovens, or separate kitchens

Timeless Construction counts these as hard costs only, meaning the contractor's labor, materials, and subcontractors. A 1,500 square foot quick-service kitchen at $200 to $350 per square foot lands between $300,000 and $525,000. Equipment, furniture, and design fees sit outside those totals.

Specialty projects show the upper end. Timeless Construction delivered a 7,684 square foot dual-concept project for $4.75 million in 150 days. It included two full commercial kitchens and charcoal grilling.

The graphic below repeats the three ranges next to the national figure.

Commercial kitchen hard construction cost per square foot for quick-service, full-service, and specialty restaurant concepts

Cost per square foot depends on the systems behind the walls, so the next section breaks down what those systems are.

What Systems Drive Commercial Kitchen Build Out Costs?

Mechanical, electrical, and plumbing systems drive kitchen build out costs, and hood and ventilation work sits inside that share. Builders Group Construction puts mechanical, electrical, and plumbing work at about 45 to 55 percent of hard cost. That figure comes from its source data. Kitchen equipment accounts for about 22 to 30 percent.

A Type I hood collects grease vapors and smoke above fryers, grills, and griddles. Terrapin Construction Group reports hood installation at $5,000 to $20,000, with a 10-foot hood at $10,000 to $12,000. Fire suppression adds $2,000 to $5,000, and ductwork, rooftop units, and make-up air can push ventilation past $30,000 to $50,000.

The graphic below lists the major kitchen line items with their published ranges.

Commercial kitchen line item costs for Type I hood, fire suppression, walk-in cooler, dishwasher, and equipment package

Walk-in coolers cost $8,000 to $30,000 and commercial dishwashers $3,000 to $20,000, according to a Bay Area pricing guide from Custom Home. Shell condition changes these totals. A second-generation space may already hold a hood and grease trap, per Builders Group Construction. An undersized unit can still need work.

Terrapin Construction Group reports that converting an existing space costs 30 to 50 percent less than new construction. A tenant buildout contractor can inspect the hood, grease trap, and utilities before a lease is signed. That inspection shows which costs the shell already covers and which it adds.

How Much Does It Cost to Build a Restaurant Kitchen From Shell to Opening?

The cost to build a restaurant kitchen from shell to opening stacks hard cost, equipment, and soft costs. Timeless Construction lists a basic quick-service equipment package from about $75,000. A full-service kitchen with multiple cooking lines and walk-in coolers runs $200,000 to $500,000 or more.

Soft costs add 12 to 20 percent of hard construction cost, according to Timeless Construction. That share covers design, permitting, health department plan review, fire marshal review, utility connections, and insurance. Design fees alone run 6 to 8 percent of construction cost. On a $300,000 hard cost, soft costs add $36,000 to $60,000.

Written build out estimates should list each kitchen system as its own line. Separate lines let owners compare bids on the same scope. Builders Group Construction advises defining scope in writing, because the phrase build out cost means different scopes to different contractors.

Benchmarks for other building types add context. Owners can review construction cost benchmarks for offices and retail before setting the kitchen budget.

Construction cost is only part of the schedule, so the next section covers timing.

How Long Does a Commercial Kitchen Build Out Take?

Construction takes 60 to 90 days for a quick-service shell. Permitting adds 30 to 60 days, according to Timeless Construction. A full-service ground-up restaurant takes 120 to 180 days of construction plus 60 to 90 days of pre-construction and permitting. Equipment lead times run 8 to 16 weeks, so orders must start early. Timeless Construction calls late equipment ordering the most common schedule failure on its projects.

The steps on how to build a commercial kitchen follow one order.

  1. Finalize the menu and equipment list before drawings begin.
  2. Submit plans for health, building, and fire review.
  3. Order equipment within 14 days of the construction start.
  4. Build the rough-in plumbing, electrical, gas, and ventilation, then the finishes.
  5. Pass the final fire, building, and health inspections.

The graphic below shows the same five steps with the timing figures.

Commercial kitchen build out timeline from plan review and permitting to equipment ordering, construction, and inspections

Design changes after drawings are complete add 4 to 8 weeks and $30,000 to $80,000, per Timeless Construction. Owners can pair the schedule with a design-build contractor, who prices the kitchen during design. Early pricing exposes cost conflicts while the drawings can still change.

Equipment deliveries, rough-in inspections, and finish trades compete for the same weeks. Sequencing equipment orders against the rough-in is construction management work.

Each step above depends on approvals, so the next section covers the rules.

What Are the Rules for a Commercial Kitchen in Florida?

The rules for a commercial kitchen in Florida come from state food service law, the Florida Building Code, and fire codes. Several agencies review one kitchen, and each one can ask for changes. Local code may be stricter than any summary here.

  • Plan review: the state Division of Hotels and Restaurants sets rules for approving food service facility plans (Section 509.032, Florida Statutes).
  • Plumbing: Section 509.221 requires food service plumbing to follow the Florida Building Code, as approved by the local building authority.
  • Hood and duct: a Type I hood goes above grease-producing appliances, and NFPA 96 Chapter 11 sets cleaning intervals.
  • Code cycle: the Florida Building Code 9th Edition takes effect December 31, 2026, according to the Miami-Dade Permitting and Inspection Center.
  • Accessibility: 28 CFR 36.403 caps path of travel upgrades at 20 percent of the alteration cost for a primary function area.

Local permitting rules depend on the scope, so a kitchen with new gas, exhaust, and plumbing lines needs several permits. The building and fire offices review each one separately.

Jurisdictions publish their own permit fee schedules, and those fees add to soft costs. Budget for plan review, inspections, and any re-inspection visits.

Hood inspection intervals become a recurring operating cost. The table below uses the City of Bellevue fire prevention handout, which summarizes the International Fire Code and NFPA 96 Chapter 11.

Hood and Duct Inspection Intervals by Cooking Operation
Cooking OperationInspection Interval
Solid-fuel cooking appliances1 month
High-volume operations such as 24-hour cooking, charbroiling, or wok cooking3 months
All other cooking operations6 months
Low-volume operations such as seasonal businesses12 months

The same handout requires pre-engineered fire-extinguishing systems to be tested at least every 6 months. Inspection and cleaning records stay on the premises for 3 years. Confirm the adopted fire code edition with your local fire official before design starts.

What Hidden Costs Can Raise a Kitchen Build Out Budget?

Hidden costs raise a kitchen build out budget when site conditions and utility capacity differ from the drawings. Builders Group Construction lists several sources of cost beyond the original estimate. A kitchen general contractor reviews each source during pricing.

  • Electrical capacity upgrades for cooking and refrigeration equipment.
  • Gas service and plumbing modifications.
  • Hood and ventilation requirements that exceed the existing system.
  • A grease interceptor that needs installation or replacement.
  • Fire suppression changes and code compliance updates.
  • Design changes, material upgrades, and unforeseen conditions.

Some costs sit outside a construction quote entirely. Builders Group Construction lists furniture, signage, design fees, permits, lease deposits, inventory, and working capital. A quote can exclude any of them. Confirm in writing which of these items the contractor's price includes.

An opening budget adds those items to the build out cost, so owners separate the two numbers early. Keep a contingency reserve for unforeseen conditions, since concealed utilities appear only after demolition. Reserves cover the surprises, and the next section covers ways to lower the base number.

How Can Owners Reduce Kitchen Build Out Costs?

Owners reduce kitchen build out costs by fixing the equipment list before drawings start. Timeless Construction explains that the kitchen drives the mechanical, electrical, and plumbing design for the whole building. Late equipment changes then force redesign.

  • Choose a second-generation space, which Terrapin Construction Group reports costs 30 to 50 percent less than new construction.
  • Lock subcontractor pricing within 30 days of the bid, as Timeless Construction recommends.
  • Order equipment within 14 days of the construction start to match the rough-in schedule.
  • Specify ENERGY STAR certified equipment, which the program says could save about 350 MMBTU per year, or about $4,000 per year.
  • Negotiate landlord allowances before signing, since they can offset part of the kitchen cost.

Each of these steps protects the budget before demolition begins, and the remaining questions cover specific cases.

What Else Should You Know About Kitchen Build Outs?

How Much Does It Cost to Set Up a Commercial Kitchen?

The cost to set up a commercial kitchen combines construction with $75,000 to $500,000 or more in equipment. Timeless Construction sets the low end at a basic quick-service package. Add soft costs of 12 to 20 percent of hard cost.

How Much Does It Cost to Build a Small Commercial Kitchen?

The cost to build a small commercial kitchen of 1,000 square feet runs $200,000 to $350,000 in hard cost at quick-service rates. That total comes from multiplying 1,000 square feet by $200 to $350 per square foot. A small commercial kitchen build out in a second-generation space can cost less, because hood and grease trap work may already exist.

What Is a Good Size for a Commercial Kitchen?

A good size for a commercial kitchen is the footprint the menu and equipment list require. A fryer line, walk-in cooler, and dish station each claim fixed floor space. Size the kitchen from the equipment plan, then fit the dining room around it.

How Should a Commercial Kitchen Be Laid Out?

A commercial kitchen should be laid out around one-directional food flow from receiving to storage, prep, cooking, plating, and dishwashing. Assembly line, island, zone, and galley layouts all follow that sequence. Hotel restaurants apply the same flow during a hotel kitchen renovation.

What Is the 3 Kitchen Rule?

The 3 kitchen rule is the work triangle that links the sink, the cooktop, and the refrigerator. Residential designers use the triangle. Commercial kitchens plan stations and traffic paths instead, because several cooks share the space.

What Are Commercial Kitchen Build Out Ideas That Cut Cost?

Ideas that cut cost include one shared hood line, a compact cooking line, and a second-generation shell. Each idea reduces ductwork, equipment, or demolition. The design team confirms every idea against the health and fire reviews.

Can I Turn My Garage Into a Commercial Kitchen?

Yes, a garage can become a commercial kitchen only when zoning, building, and health rules all allow the use. Florida offers a separate path for small home food businesses. Section 500.80, Florida Statutes, exempts cottage food operations from state permitting up to $250,000 in annual gross sales. Those operations must follow the home-based business rules in Section 559.955.

Can You Build a Commercial Kitchen in Your Home?

Yes, you can build a commercial kitchen in your home when zoning, building code, and health review all approve. Zoning comes first, and local rules vary. Ask the permit office and DBPR before spending money on design.

Can I Build a Commercial Kitchen on My Property?

Yes, you can build a commercial kitchen on your property when the zoning allows food service use on the parcel. Building permits and food service plan approval still apply. A property survey and a zoning letter come first.

How Does MT Construction Group Help With a Commercial Kitchen Build Out?

We build kitchens from the equipment plan outward, so every hood, drain, and circuit has a place before work starts. As a restaurant kitchen contractor, our team coordinates design, permits, and trades under one schedule. Each phase is inspected before the next begins.

Owners who want a written scope for their kitchen can start with MT Construction Group. We price each kitchen from its equipment list and publish no flat rates, because every concept differs.

Link copied!